Office

Phone Payments

New Electric Connections

Download PDF Flowchart

Electric Connection Steps for New Construction

  • 1

    Stake the location of your new home

  • 2

    Talk to LUS Engineering

  • 3

    LUS spots temporary service

    If sewer is available skip to step 6

  • 4

    Apply for septic tank at the health dept.

  • 5

    Bring yellow copy to LUS

  • 6

    Customer sets temp service rig

  • 7

    Pay inspection fee, deposit, cut in fee

    If less than 500 feet of line is needed skip to step 9

  • 8

    Pay construction costs

  • 9

    Customer pours footer

  • 10

    Temporary service is inspected

  • 11

    Power is connected as soon as possible

  • 12

    Customer frames & wires house

  • 13

    Rough in inspection is performed

  • 14

    Customer completes electrical

  • 15

    Final inspection is performed

    If inspection passes skip to step 18

  • 16

    Customer fixes problem(s)

  • 17

    Pay for a repeat final inspection

    If repeat inspection fails go to step 16

  • 18

    Permanent power is connected